The main civil operations up to and including basement car park slab and associated drainage have now been completed, with the concrete Frame commencing within the reporting period.
Phase 1
- Block D - 3rd floor completed
- Block E - 1st floor completed, walls and columns 1st to 2nd floor currently progressing
- Block F - 1st floor completed, walls and columns 1st to 2nd floor currently progressing
Phase 2
- Civil operations to basement completed
- Basement walls, columns, and cores progressing
- Podium slab progressing
The concrete frame operations are currently taking a two week period to commence and complete each floor.